General Information

Structural Type: Extradosed bridge
Function / usage: Road bridge
Other name(s): Pyung-Yeo 2 Gyo
Construction began in: 2002
Status: under construction

Geographic Information & Related Structures

Location: Yeosu, Jeollanam-do, South Korea, Asia

Technical Information

Dimensions

main span 120 m
width 23.50 m
total length 250 m
span lengths 65 m - 120 m - 65 m

Materials

deck prestressed concrete
piers reinforced concrete

Chronology

2000 - 2002

Design phase.

Notes

Pyung-Yeo 2 Gyo is the first Extradosed Bridge in Korea. The construction period is expected to be about 39 months and construction began September, 2002. It is a turn-key project for which SK Engineering & Construction won the first prize.

Participants

Design
Construction

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • Masterton, Iain Slender solution, in "Bridge Design & Engineering", 2nd Quarter 2006, n. 43 v. 12

Internal Information

Structure-ID: s0007327
Created: 29/12/2002
Last Updated: 05/03/2013