Other name(s): Arade River Bridge
Beginning of works: April 1988
Completion: 13 September 1991
Status: in use

Project Type

Location

Location: , ,
Crosses:
  • Arade River
Coordinates: 37° 9' 3.52" N    8° 30' 4.54" W
Coordinates: 37° 9' 6.26" N    8° 30' 38.80" W
Show coordinates on a map

Technical Information

Dimensions

total length 842.00 m
deck deck depth 1.60 m
deck width 15.18 m
eastern approach viaduct total length 231.00 m
span lengths of eastern approach viaduct 24 m - 6 x 30 m - 27m
pylon pylon height 61.50 m
western approach viaduct span lengths 27 m - 3 x 30 m - 24m
number of spans 5
length of western approach viaduct 141.00 m
main bridge
main span 256.00 m
length 470.00 m
span lengths of main bridge 107 m - 256 m - 107 m

Quantities

reinforcing steel 300 t
reinforcing steel 1 400 t
steel for cable-stays 290 t
concrete for foundations (except piles) 8 000 m³
concrete for pylons and piles 2 800 m³
prestressing bars 125 t
prestressing for deck 190 t
deck concrete volume 8 800 m³

Materials

deck prestressed concrete
foundations reinforced concrete
pylons reinforced concrete
pylon pile caps prestressed concrete

Chronology

April 1988

Construction begins.

Participants

Stay cables
(role unknown)
Monitoring (2005)
Monitoring equipment

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

More publications...
  • About this
    data sheet
  • Structure-ID
    20002325
  • Published on:
    12/11/2001
  • Last updated on:
    05/02/2016
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine